Maximum Demand for Buildings

Estimating maximum demand is a topic frequently discussed. Working out how much power to allow for a building in my experience a very subjective . Allowing too much power results in additional equipment, increased space requirements, greater system losses and extra cost. On the other side, not enough power results in operational problems. Trying to find the right amount of power is like gazing into a crystal ball and everyone will see something different.
Early in a project power demand is estimated on a w/m2 basis. Each building needs to be considered on it merits and appropriate allowances worked out (for example a office designed for high end banking clients will require more power than a general purpose office). While there are no fixed guidelines it is good to have some sort of starting point. The table below is something I have put together as an initial set of demand figures to start playing with. Hopefully it may help someone or at least give some food for thought.
In putting the table together I used the area descriptions and maximum lighting power densities from ASHRAE 90.1-2007 (Energy Standard for Buildings). For the power densities I sought guidance and extrapolated from Siemens Application Manual - Basic Data and Preliminary Planning, 2006.  Major plant and equipment such as chillers, fire pumps, etc. should be estimated separately.


 LightingPower
Space(W/m2)SF(W/m2)SF2
Atrium - First Three Floors60.8590.3
Atrium - Floors (above first 3)20.8590.3
Audience/Seating Area - Convention Centre80.8550.3
Audience/Seating Area - Exercise Centre30.8550.3
Audience/Seating Area - General100.8550.3
Audience/Seating Area - Gymnasium40.8550.3
Audience/Seating Area - Motion Picture Theatre130.8550.3
Audience/Seating Area - Penitentiary80.8550.3
Audience/Seating Area - Performing Arts Theatre280.8550.3
Audience/Seating Area - Religious Buildings180.8550.3
Audience/Seating Area - Sports Arena40.8550.3
Audience/Seating Area - Transportation50.8550.3
Automotive-Service/Repair80.85720.6
Bank/Office-Banking Activity Area160.85540.6
Classroom/Lecture/Training - General150.85150.6
Classroom/Lecture/Training - Penitentiary140.85150.6
Conference/Meeting/Multipurpose140.85260.8
Convention Centre-Exhibit Space140.85260.8
Corridor/Transition - General50.85100.3
Corridor/Transition - Hospital110.85100.3
Corridor/Transition - Manufacturing Facility50.85100.3
Courthouse - Confinement Cells100.8500
Courthouse - Courtroom200.85200.8
Courthouse - Judges' Chambers140.85200.8
Dining Area - Bar Lounge/Leisure Dining150.85100.3
Dining Area - Family Dining230.85100.3
Dining Area - General100.85100.3
Dining Area - Hotel140.85100.3
Dining Area - Motel130.85100.3
Dining Area - Penitentiary140.85100.3
Dormitory-Living Quarters120.85180.6
Dressing/Locker/Fitting Room60.85100.3
Electrical/Mechanical160.85150.3
Exterior -  Stairways10.80.8500
Exterior - Building Facades (illuminated)2.20.8500
Exterior - Building Facades (non-illuminated)00.8500
Exterior - Canopies/Overhangs13.50.8500
Exterior - Entrances/Inspection Station13.50.8500
Exterior - Loading Areas5.40.8500
Exterior - Sales Areas5.40.8500
Exterior - Uncovered Parking Area1.60.8500
Exterior - Walkways (< 3m wide)9.90.8500
Exterior - Walkways (≥3 m wide)2.20.8500
Fire Stations - Engine Room90.85150.3
Fire Stations - Sleeping Quarters30.85180.6
Food Preparation130.853870.8
Gymnasium/Exercise Centre - Exercise Area100.85200.6
Gymnasium/Exercise Centre - Playing Area150.85150.6
Hospital - Emergency290.853600.6
Hospital - Exam/Treatment160.853600.6
Hospital - Laundry-Washing60.853600.6
Hospital - Medical Supply150.853600.6
Hospital - Nursery60.853600.6
Hospital - Nurses' Station110.853600.6
Hospital - Operating Room240.853600.6
Hospital - Patient Room80.853600.6
Hospital - Pharmacy130.853600.6
Hospital - Physical Therapy100.853600.6
Hospital - Radiology40.853600.6
Hospital - Recovery90.853600.6
Hotel/Motel Guest Rooms120.85180.6
Laboratory150.853600.6
Library - Card File and Cataloguing120.85380.6
Library - Reading Area130.85320.6
Library - Stacks180.85320.6
Lobby - General140.8510.3
Lobby - Hotel120.85181
Lobby - Motion Picture Theatre120.85181
Lobby - Performing Arts Theatre360.85181
Lounge/Recreation - General130.8520.3
Lounge/Recreation - Hospital90.8560.3
Manufacturing - Control Room50.85720.6
Manufacturing - Detailed Manufacturing230.85720.6
Manufacturing - Equipment Room130.85720.6
Manufacturing - High Bay (≥7.6 m)180.85720.6
Manufacturing - Low Bay (<7.6 m)130.85720.6
Museum - General Exhibition110.85690.6
Museum - Restoration180.85620.6
Office -Enclosed120.85280.8
Office -Open Plan120.85280.8
Parking Garage-Garage Area20.8580.6
Penitentiary - Confinement Cells100.8500
Penitentiary - Courtroom200.85200.8
Penitentiary - Judges' Chambers140.85200.8
Police Station - Confinement Cells100.8500
Police Station - Courtroom200.85200.8
Police Station - Judges' Chambers140.85200.8
Post Office-Sorting Area130.85720.6
Religious Buildings - Fellowship Hall100.8550.3
Religious Buildings - Worship Pulpit, Choir260.8550.3
Restrooms/Toilets100.8551
Retail Mall Concourse180.85420.6
Sales Area (for accent lighting)180.8500
Sports Arena - Court Sports Area250.8550.6
Sports Arena - Indoor Playing Field Area150.8550.6
Stairs60.8590.3
Storage Active - General90.660.3
Storage Active - Hospital100.660.3
Storage Inactive - General30.460.3
Storage Inactive - Museum90.460.3
Transportation - Air/Train/Bus Baggage Area110.85191
Transportation - Airport Concourse60.85241
Transportation - Terminal Ticket Counter160.85141
Warehouse - Fine Material Storage150.8550.6
Warehouse - Medium/Bulky Material Storage100.8550.6
Workshop200.85720.6